I need to make simulation of producing three types of parts (A, B and AB) in Tecnomatix Plant Simulation. How to make order on Drain what to produce on previous stations to get wanted part? I have two sources (one for part A and one for part B, part AB is assembled of parts A and B).
Answer by
Swati Dubey
To make the pull method produce the exact number of entities, you can use the "Pull with Transporter" element and set the "MaxLoad" attribute to the desired number of entities. To order the drain what to produce on previous stations, you can use the "Material Flow" element and set the production orders accordingly.
I need to make simulation of producing three types of parts (A, B and AB) in Tecnomatix Plant Simulation. How to make order on Drain what to produce on previous stations to get wanted part? I have two sources (one for part A and one for part B, part AB is assembled of parts A and B).
To make the pull method produce the exact number of entities, you can use the "Pull with Transporter" element and set the "MaxLoad" attribute to the desired number of entities. To order the drain what to produce on previous stations, you can use the "Material Flow" element and set the production orders accordingly.